Deviation settlement mechanism

The deviation settlement mechanism is the set of charges that a generator or buyer on the grid pays or receives when the electricity it actually injects or draws differs from its schedule. It gives grid users a commercial reason to stick to their schedules, which helps keep the grid stable.

For entities connected to the inter-state grid it is governed by the Central Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2024, published in the Gazette of India on 21 August 2024 and in force from 16 September 2024. State commissions set their own rules for deviation within a state.

Deviation is worked out for each time block of the day as the gap between actual and scheduled injection for a seller, or actual and scheduled drawal for a buyer. Under the regulations, the system operator generally manages deviation through ancillary services, and the charges for it are settled under these regulations.

Wind and solar sellers have their deviation measured against available capacity rather than against their schedule. The Commission's Statement of Reasons of 15 November 2024 said this formula would apply up to 31 March 2026, after which it was to move to scheduled generation in phases through separate orders. Check the Commission's later orders for the current position.

Where this goes further

Related terms

All 130 terms